    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

  • 04
    09/04

    Collection System Rehab

    All day
    09/04-11/29

    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

  • 05
    09/05

    Collection System Rehab

    All day
    09/05-11/30

    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

  • 06
    09/06

    Collection System Rehab

    All day
    09/06-12/01

    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

  • 07
    09/07

    Collection System Rehab

    All day
    09/07-12/02

    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

Sewer System Improvements

Pleasant Valley Kissel Hill Sewer Extension

This project involves an upgrade of an interceptor in Manheim Township as part of a larger construction contract for the extension of public sewer to the areas of Pleasant Valley and Kissel Hill Road in Manheim Township. The design and construction management engineering contract was awarded to Buchart Horn at the July 2010 Board meeting, and the resident inspection contract was awarded to Buchart Horn at the March Board meeting. The general construction contract was awarded to Mazucca Enterprises at the May 2012 Board meeting.

The schedule shows completion of the project in early December, although the contract deadline is February 7, 2013.

Contractor Contract Contract Amount
Buchart Horn
Design
$147,500.00
Buchart Horn
CM and RPR
$146,400.00
Mazucca Enterprises, Inc.
Construction
$2,191,465.00
Total
$2,485,365.00

Master Capital Asset Plan

This project involves LASA-wide capital and asset planning. The contract was awarded to EMA at the July 2010 Board meeting.

Contractor Contract Contract Amount
EMA
Study
$62,600.00

Sewer Main Rehabilitation 2012

This project consists of the lining of 6,500 linear feet of 8 inch sewer main and 860 feet of ten inch sewer main, and the reconnection of 145 sewer service lines. The contract was awarded to AM-Liner East, Inc. at the October 25, 2012 LASA Board meeting.

Contractor Contract Contract Amount
AM-Liner East, Inc.
Construction
$233,994.00

Manhole Rehabilitation 2012

This project consists of the rehabilitation of 15 manholes using spray applied resin lining. The contract was awarded to Abel Recon at the October 25, 2012 LASA Board meeting.

Contractor Contract Contract Amount
Abel Recon
Construction
$47,858.10

Lateral Replacement 2012

This project consists of the replacement of 60 laterals, most on Savo Drive in Manheim Township, plus installation of two new laterals in East Hempfield Township for the mandatory connection requirements (Korig and Oatman). The contract was awarded to Koser Excavating at the October 25, 2012 LASA Board meeting.

Contractor Contract Contract Amount
Koser Excavating
Construction
$271,500.00

Pump and Motor Rebuild 2012

This project consists of the rebuilding of the last Charlestown Pump (3 have been previously rebuilt). The contract was awarded to A.C. Schultes at the October 25, 2012 LASA Board meeting.
Contractor Contract Contract Amount
A.C. Schultes
Repair
$29,245.00