Quick Links

Upcoming Events

< 2023 >
July
«
»
  • 05
    07/05

    Collection System Rehab

    All day
    07/05-10/29

    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

  • 06
    07/06

    Collection System Rehab

    All day
    07/06-10/30

    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

  • 07
    07/07

    Collection System Rehab

    All day
    07/07-10/31

    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

  • 10
    07/10

    Collection System Rehab

    All day
    07/10-11/03

    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

  • 11
    07/11

    Collection System Rehab

    All day
    07/11-11/04

    Project consists of relining approximately 16,500 feet of 8″ diameter sewer main in Manor Township and Columbia Borough. LASA has contracted with Mr Rehab from Mechanicsburg Pa to perform the work.  Notices will be given prior to any work being performed and any questions can be directed to the Authority.

Charges and Fees

Fee Description
Sewer Service Request
$225
Required escrow deposit payable at time of sewer service request submission. Review will be billed on a time and cost basis. Unexpended escrow deposit funds will be refunded. Additional funds may be required if review exceeds initial escrow deposit.
Development Review
$1000
Required escrow deposit payable at time of preliminary plan submission. Review will be billed on a time and cost basis. Unexpended escrow deposit funds will be refunded. Additional funds may be required if review exceeds initial escrow deposit.
Construction Permit
$1000
The construction permit fee is payable at time of procurement.
Lateral Inspection
$75
The fee for a lateral inspection is payable at the time a connection permit is acquired. If the scheduled inspection should fail or if the inspector is required to perform more than one (1) inspection the additional fee will be as follows: $75.00
Construction Inspection (Per Hour)
$31
The fee for construction inspections will be based on an hourly rate for an Authority Inspector. Mileage will be billed at $0.56 per mile (year 2021). The hourly rate for an authorized representative of the Authority will be based upon then current rate for the representative's firm.
Tapping Fee (Residential)
$3927
Per equivalent dwelling unit
Tapping Fee (Commercial)
$16.50
Per gallon (minimum of 238 gallons)
Connection Fee
$750